Implementation of the computer complex project
Projects 24.06.2026

Problem

A top-10 Russian bank required the deployment of a computing complex for AI and HPC workloads. The solution needed to consist of internal and external segments—physically isolated from from each other, with the possibility to switch nodes from one segment to another. The internal segment is located within the bank’s information system perimeter and connected to an internal object storage system. The external segment must be moved beyond the IT infrastructure and include dedicated management nodes and data storage. The solution had to meet the the customer's information security requirements.

The internal segment is focused exclusively on AI-related tasks using containerization technology, while the external segment is versatile and includes HPC workloads support. The configuration of all nodes must be identical. The architecture of the computing complex is a hybrid cluster with support for a hyperconvergent environment with the capability for future expansion.

 

Solution

The joint team of "E-Phlops" and "AMDtechnologies" created and commissioned a computing cluster consisting of 22 computing nodes. Each node is a dual-processor x86-based server featuring 96 cores per socket, 8 Nvidia H100 GPU accelerators, and NVMe SSD storage.

The network infrastructure is built on three physically separated networks. For high-speed exchange between nodes and connection of the external the storage system of the external segment, InfiniBand HDR with a total throughput of at least 1600 Gbit/s per node in one direction with unblocked access is used in the Fat Tree topology. For local area network connectivity, 25 GB Ethernet is used and 10 GB Ethernet is used. Additionally, a 32 Gb/s Fibre Channel storage network has been deployed in the internal segment for connection to object storage.

The storage subsystem for the external segment is implemented using a dedicated storage system that supports hierarchical storage. The internal segment uses a distributed hyper-convergent storage. 

The software stack includes monitoring and management tools (such as NVIDIA DCGM for GPU monitoring), a data visualization and analysis system based on open-source packages, and a Kubernetes orchestration platform (K8s) with Multus and Cilium modules. The external segment additionally supports the Slurm task scheduler. The managing servers run in a virtual environment called Proxmox. 

The project included:

•        Site survey

•        Architectural design of the computing complex

•        Creation a complete solution project

•        Supply of necessary equipment

•        Implementation of the computing complex, including installation and cabling/interconnection work

•        Commissioning, including functional and load testing

•        Acceptance testing, with a separate phase for information security

•        Training of the customer's engineers in the use of the computing complex

•        Handover for ongoing maintenance and support

 

Result

For 9 months, a computing complex was created that meets the customer's requirements regarding performance, fault tolerance, functionality, and information security. This computing cluster enabled the deployment of all necessary services for the bank’s main division; it also allowed branches to connect to the system, granting them access to the supercomputer’s processing power for running their own high-load applications.

 

Сomputing cluster (supercomputer) in figures


•     700+ active users

•     22 compute nodes

•     11,792 Tflops (FP64)

•     700 PFlops (FP8/INT8)

•     4,224 processor cores

•     33,792 GB of compute node RAM

•     14,080 GPU RAM

•     2,973,696 CUDA cores

•     92,928 tensor cores

•     200 GB/s Infiniband HDR network

•     61 TB hot data storage

•     2 PB cold data storage

 

 

 


The E-Flops team has the most extensive experience in Russia in the implementation of world-class supercomputing projects (including those included in the Top 500 list of the most powerful publicly known computing systems in the world):

  • 1. Lomonosov Moscow State University:
    • • Lomonosov-1, performance 0.9 PFLOPS, peak performance — 1.7 PFLOPS;
    • • Lomonosov-2, performance 2,478 PFLOPS, peak performance — 4,947 PFLOPS.
  • 2. MCC of Roshydromet, performance 1,3 PFLOPS.
  • 3. JSC "Supercomputer Simulation Center", peak performance — 1,5 PFLOPS.
  • 4. NRC "Kurchatov Institute", peak performance — 1,4 PFLOPS.
  • 5. JSC “Power machines”, performance — 170 TFLOPS.

Creating a supercomputer is always an individual project with numerous requirements and limitations. First and foremost, it is limited by budget; furthermore, it is constrained by technical and infrastructural factors—such as the specifications of the data center facility, the placement of external cooling system components, as well as energy, environmental, and other limitations. Key requirements include performance, fault tolerance, compatibility with the required software, provision of all types of security, scalability, manageability, and energy efficiency. Creating a supercomputer is a complex engineering process that encompasses many stages, starting from defining objectives, design and modeling to implementation, testing, and providing support.

Our team is ready to implement the full range of services for creating a supercomputer, or to handle specific stages of the process.

Stage 0. Pre-project assessment and requirements collection (Discovery)

  • Analysis of the customer's objectives: defining the intended purpose (scientific computing, AI, engineering, cryptography, etc.).
  • Performance calculations: Set peak (Rpeak) and actual (Rmax) performance requirements (FLOPS or TOPS).
  • Audit of restrictions: assessment of the budget, available space, limits on electrical capacity to be supplied, noise and safety regulations.
  • Resource assessment: scheduling the supply of equipment (including logistical risks).

Stage 1. Logical and Physical Architectural Design (Hardware & Network)
  • Selection of the computing subsystem:definition of homogeneous (CPU) or heterogeneous architecture (combination of CPU + xPU), selection of processor cores, development of specifications for motherboards and power supply units for blade servers.
  • Define the supercomputer assignment (AI/ML or HPC tasks).
  • Define the architecture and select specific CPU and xPU models, and specifying the required quantities.
  • Define information security requirements and design the information security and information security subsystem.
  • Interconnect (data network) design: development a high-speed bus topology (selection of InfiniBand, calculation of bandwidth and latency for tens/hundreds/thousands of nodes).
  • Data storage system: selection of storage architecture (NAS, parallel file system, S3-compatible object storage, etc.), selection of software and hardware components, design of complex solution and backup subsystem.

Stage 2. Facility Infrastructure Design
  • Power Supply: calculation of power consumption; design of input distribution units and uninterruptible power supply (UPS) systems, including diesel generators.
  • Cooling System: selection of the cooling type—precision air cooling (for medium-density racks) or direct-to-chip liquid/immersion cooling (for high-heat-output GPU clusters). Heat load calculation (ranging from hundreds of kW to MW) and type of cooling (free cooling or compressor-based cooling).
  • Placement: calculation of bearing capacity of machine room floors, zoning of "hot/cold" corridors and mapping of server cabinets (Rack layout).

Stage 3. Software ecosystem design (System Software Stack)
  • Base Software: selection of a Linux distribution (kernel build with support for NUMA, large memory pages, RTOS elements, etc.).
  • Resource management system: approval of task planners and queue systems (e.g., Slurm as the primary open-source solution).
  • Virtualization, containerization platforms, orchestrators (OpenStack, OpenNebula, Kubernetes, etc.).
  • Parallel computing environments: Integration of libraries (e.g., Intel MPI, Open MPI, NCCL/RCCL, Gloo, etc.) to run distributed computing and frameworks (PyTorch, TensorFlow, JAX, etc.).
  • Management services: administration tools, node and infrastructure health monitoring systems, setting up authorization/authentication modules, user login subsystems, etc.

Stage 4. Prototyping and Software Simulation (PoC)
  • Mini-cluster assembly: Install a pilot segment of multiple reference nodes to verify compatibility of CPU/GPU components with the selected Linux distribution.
  • Profiling and benchmarking: running synthetic tests (HPL, HPCG, etc.) to identify bottlenecks in data and memory tires.
  • Software optimization: debugging the software ecosystem (System Software Stack) and fine-tuning compilers and network drivers for specific hardware (calibration of kernel parameters).

Stage 5. Equipment supply and physical installation (Deployment)
  • Acceptance and incoming inspection: verifying of supplied server equipment, switches and cable system.
  • Site preparation: modernization of the premises (construction work, installation of engineering infrastructure (Facility).
  • Rack integration: physical installation of compute nodes, management and service servers, storage hardware components, etc.
  • Cable switching: routing thousands of optical/copper interconnect cables, strictly according to approved topology (with labeling for future maintenance).

Stage 6. Commissioning and Software Integration
  • Low-level debugging: BIOS/UEFI firmware, RAID configuration, network initialization and testing.
  • Deployment and configuration of system software: OS installation on control nodes, deployment of the software ecosystem (System Software Stack).

Stage 7. Verification & Validation
  • Final benchmarking: official measurement of performance (Rmax) and energy efficiency (GFlops/Watt).
  • Stress testing: 100% power system run within 72+ hours to detect hidden chip defects, overheat or voltage drops.
  • Task-based calibration: adaptation of system parameters to the actual scientific/commercial loads of the customer (load balancing between nodes).

Stage 8. Commissioning, Training, and Technical Support (Operations & Handover)
  • Commissioning: transitioning the system to standard operational mode, pilot projects launched.
  • Training of customer personnel: Administration level: work with scheduler, monitor node status, firmware updates; Operation level: instructing performers on submitting tasks in the queue and working with the software ecosystem (System Software Stack).
  • Maintenance schedule: handover of operation manual, appointment of system administrator (chief engineer) to provide 24/7 support (SLA).
  • Warranty stand: agreement of the schedule of scheduled TO, regulations for replacement of defective components (HDD/SSD/fans) and monitoring of cooling performance.