Creating a supercomputer is always an individual project with numerous requirements and limitations. First and foremost, it is limited by budget; furthermore, it is constrained by technical and infrastructural factors—such as the specifications of the data center facility, the placement of external cooling system components, as well as energy, environmental, and other limitations. Key requirements include performance, fault tolerance, compatibility with the required software, provision of all types of security, scalability, manageability, and energy efficiency. Creating a supercomputer is a complex engineering process that encompasses many stages, starting from defining objectives, design and modeling to implementation, testing, and providing support.
Our team is ready to implement the full range of services for creating a supercomputer, or to handle specific stages of the process.
Stage 0. Pre-project assessment and requirements collection (Discovery)
- Analysis of the customer's objectives: defining the intended purpose (scientific computing, AI, engineering, cryptography, etc.).
- Performance calculations: Set peak (Rpeak) and actual (Rmax) performance requirements (FLOPS or TOPS).
- Audit of restrictions: assessment of the budget, available space, limits on electrical capacity to be supplied, noise and safety regulations.
- Resource assessment: scheduling the supply of equipment (including logistical risks).
Stage 1. Logical and Physical Architectural Design (Hardware & Network)
- Selection of the computing subsystem:definition of homogeneous (CPU) or heterogeneous architecture (combination of CPU + xPU), selection of processor cores, development of specifications for motherboards and power supply units for blade servers.
- Define the supercomputer assignment (AI/ML or HPC tasks).
- Define the architecture and select specific CPU and xPU models, and specifying the required quantities.
- Define information security requirements and design the information security and information security subsystem.
- Interconnect (data network) design: development a high-speed bus topology (selection of InfiniBand, calculation of bandwidth and latency for tens/hundreds/thousands of nodes).
- Data storage system: selection of storage architecture (NAS, parallel file system, S3-compatible object storage, etc.), selection of software and hardware components, design of complex solution and backup subsystem.
Stage 2. Facility Infrastructure Design
- Power Supply: calculation of power consumption; design of input distribution units and uninterruptible power supply (UPS) systems, including diesel generators.
- Cooling System: selection of the cooling type—precision air cooling (for medium-density racks) or direct-to-chip liquid/immersion cooling (for high-heat-output GPU clusters). Heat load calculation (ranging from hundreds of kW to MW) and type of cooling (free cooling or compressor-based cooling).
- Placement: calculation of bearing capacity of machine room floors, zoning of "hot/cold" corridors and mapping of server cabinets (Rack layout).
Stage 3. Software ecosystem design (System Software Stack)
- Base Software: selection of a Linux distribution (kernel build with support for NUMA, large memory pages, RTOS elements, etc.).
- Resource management system: approval of task planners and queue systems (e.g., Slurm as the primary open-source solution).
- Virtualization, containerization platforms, orchestrators (OpenStack, OpenNebula, Kubernetes, etc.).
- Parallel computing environments: Integration of libraries (e.g., Intel MPI, Open MPI, NCCL/RCCL, Gloo, etc.) to run distributed computing and frameworks (PyTorch, TensorFlow, JAX, etc.).
- Management services: administration tools, node and infrastructure health monitoring systems, setting up authorization/authentication modules, user login subsystems, etc.
Stage 4. Prototyping and Software Simulation (PoC)
- Mini-cluster assembly: Install a pilot segment of multiple reference nodes to verify compatibility of CPU/GPU components with the selected Linux distribution.
- Profiling and benchmarking: running synthetic tests (HPL, HPCG, etc.) to identify bottlenecks in data and memory tires.
- Software optimization: debugging the software ecosystem (System Software Stack) and fine-tuning compilers and network drivers for specific hardware (calibration of kernel parameters).
Stage 5. Equipment supply and physical installation (Deployment)
- Acceptance and incoming inspection: verifying of supplied server equipment, switches and cable system.
- Site preparation: modernization of the premises (construction work, installation of engineering infrastructure (Facility).
- Rack integration: physical installation of compute nodes, management and service servers, storage hardware components, etc.
- Cable switching: routing thousands of optical/copper interconnect cables, strictly according to approved topology (with labeling for future maintenance).
Stage 6. Commissioning and Software Integration
- Low-level debugging: BIOS/UEFI firmware, RAID configuration, network initialization and testing.
- Deployment and configuration of system software: OS installation on control nodes, deployment of the software ecosystem (System Software Stack).
Stage 7. Verification & Validation
- Final benchmarking: official measurement of performance (Rmax) and energy efficiency (GFlops/Watt).
- Stress testing: 100% power system run within 72+ hours to detect hidden chip defects, overheat or voltage drops.
- Task-based calibration: adaptation of system parameters to the actual scientific/commercial loads of the customer (load balancing between nodes).
Stage 8. Commissioning, Training, and Technical Support (Operations & Handover)
- Commissioning: transitioning the system to standard operational mode, pilot projects launched.
- Training of customer personnel: Administration level: work with scheduler, monitor node status, firmware updates; Operation level: instructing performers on submitting tasks in the queue and working with the software ecosystem (System Software Stack).
- Maintenance schedule: handover of operation manual, appointment of system administrator (chief engineer) to provide 24/7 support (SLA).
- Warranty stand: agreement of the schedule of scheduled TO, regulations for replacement of defective components (HDD/SSD/fans) and monitoring of cooling performance.